Project details
- Contract Period: 4 months
- Contract Value: AED 12,000,000 (US$ 3,266,000)
- Location: Dubai Marina
- Client: EMAAR
Dubai Marina Mall Cooling Tower Upgrade
This project involved the replacement of 10 cooling towers which served 9,000 tons of cooling for the Dubai Marina Mall. The existing cooling towers were deconstructed whilst maintaining full functionality of the DMM and replaced in a live working environment. As a tower crane was not permitted for use each new cooling tower was delivered in kit format and installed and commissioned to improve the cooling efficiency of the Dubai Mall Chillers.